PROJECT 2 OPERATIONAL EXCELLENCE

GME - Maghreb-Europe Gas Pipeline

From transit agreement to national asset. Following the unilateral termination of the transit agreement on November 1, 2021, ONHYM regained control of this strategic asset and transformed it into a reliable supply infrastructure for Morocco pioneering reverse-flow operations in the region.

540 km

Morocco section length

12 bcm

Annual design capacity

100%

Uptime since June 2022

Zéro

Zéro Incident
Source
Spain

Spain

LNG procurement by ONEE
Regasification at Spanish facilities

GME · Reverse Flow
Destination
Morocco

Morocco

Tarifa exit → GME pipeline
Power plants & industrial users

Our Approach

How it happened - milestone timeline

We adopt a strategic and responsible approach to developing Morocco’s energy and mining resources, combining technical expertise, innovation, and strong partnerships to create sustainable long-term value.

September 2020
Regulatory approval secured for Tarifa exit point (Spanish & EU authorities)
April 2021
Interconnection agreement negotiated with Enagás (Spanish TSO)
2021
Technical adaptations completed to enable reverse flow capability
October 2021
Transit agreement terminated-reverse-flow preparations accelerated
June 2022
Reverse flow operations successfully commissioned with Enagás

Current expansion initiatives

Three active development projects extending GME’s reach into new power plants, the strategic Tahaddart
Thub, and Morocco’s first major domestic gas discovery at Tendrara.

ONEE Power Plant Connections

Connect existing and new generation facilities (Al Wahda, Tahaddart enhancement, other ONEE assets

  • ENGINEERING UNDERWAY

Tahaddart Spur Line

Direct connection to Tahaddart power plant.
Enhanced reliability, lower transport cost, redundancy

  • DEVELOPMENT PHASE

Tendrara Field Connection

Integrate Morocco’s first major gas discovery with the GME pipeline. Domestic supply, reduced import dependency

  • INTERCONNECTION AGREEMENT
OUR MISSION

Operational excellence - OMCo capabilities

Nomination management

Pipeline management

Control & SCADA

Regulatory compliance

Partnership management

Technical engineering